Question: Step 1: Complete the tables for Tasks 1, 2 and 3. Step 2: upload this form into ACT 4 TASK 1: Complete the following table.
Step 1: Complete the tables for Tasks 1, 2 and 3.
Step 2: upload this form into ACT 4
TASK 1: Complete the following table. Lead time for the part is 2 weeks. The lot size is 100.
Task 2: Complete the following table. Lead time for the part is 2 weeks.
Task 3: MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.

ACT 4: MRP : Step 1: Complete the tables for Tasks 1, 2 and 3. Step 2: upload this form into ACT 4 4 25 + TASK 1: Complete the following table. Lead time for the part is 2 weeks. The lot size is 100. Week 1 2 3 Gross requirements 20 65 35 Part A A Scheduled receipts 100 Lot Size:100 Projected available 30 Lead time Net requirements 2 weeks Planned order receipt Planned order release 4 10 Task 2: Complete the following table. Lead time for the part is 2 weeks. Week 1 2 2 3 Gross requirements 30 25 10 Part B Scheduled receipts 50 Lot Size:50 Projected available 10 Lead time Net requirements 2 week Planned order receipt Planned order release 1 4 Task 3: MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets. . Week 2 3 X x Gross requirements Part Y Scheduled receipts Lot Size: 50 Projected available S Lead time Net requirements 2 weeks Planned order receipt Planned order release 30 Y(1) Z(2) T 1 2 3 4 Week Gross requirements Scheduled receipts Projected available Net requirements Planned order receipt Planned order release Part 2 Lot Size: 100 Lead time 1weeks 20 ACT 4: MRP : Step 1: Complete the tables for Tasks 1, 2 and 3. Step 2: upload this form into ACT 4 4 25 + TASK 1: Complete the following table. Lead time for the part is 2 weeks. The lot size is 100. Week 1 2 3 Gross requirements 20 65 35 Part A A Scheduled receipts 100 Lot Size:100 Projected available 30 Lead time Net requirements 2 weeks Planned order receipt Planned order release 4 10 Task 2: Complete the following table. Lead time for the part is 2 weeks. Week 1 2 2 3 Gross requirements 30 25 10 Part B Scheduled receipts 50 Lot Size:50 Projected available 10 Lead time Net requirements 2 week Planned order receipt Planned order release 1 4 Task 3: MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets. . Week 2 3 X x Gross requirements Part Y Scheduled receipts Lot Size: 50 Projected available S Lead time Net requirements 2 weeks Planned order receipt Planned order release 30 Y(1) Z(2) T 1 2 3 4 Week Gross requirements Scheduled receipts Projected available Net requirements Planned order receipt Planned order release Part 2 Lot Size: 100 Lead time 1weeks 20