Question: Complete the MRP plan Lt =2. batchsize= lot for lot , SS =0 A 1 2 3 4 5 6 7 8 9 10 Gross
Complete the MRP plan
Lt =2. batchsize= lot for lot , SS =0
| A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Gross Requirements | 50 | 15 | 15 | 50 | ||||||
| Scheduled Receipts | ||||||||||
| Projected On Hand 0 | ||||||||||
| Planned Order Release |
B.)
Lt = 2 , batch size = lot for lot SS = 0
| B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Gross Requirements | 25 | 65 | 50 | 10 | 10 | 50 | 15 | 15 | 10 | 10 |
| Scheduled Receipts | ||||||||||
| Projected On Hand 150 | ||||||||||
| Planned Order Release |
List Actions that should be taken in period 1