Question: Complete the MRP plan Lt =2. batchsize= lot for lot , SS =0 A 1 2 3 4 5 6 7 8 9 10 Gross

Complete the MRP plan

Lt =2. batchsize= lot for lot , SS =0

A 1 2 3 4 5 6 7 8 9 10
Gross Requirements 50 15 15 50
Scheduled Receipts
Projected On Hand 0
Planned Order Release

B.)

Lt = 2 , batch size = lot for lot SS = 0

B 1 2 3 4 5 6 7 8 9 10
Gross Requirements 25 65 50 10 10 50 15 15 10 10
Scheduled Receipts
Projected On Hand 150
Planned Order Release

List Actions that should be taken in period 1