Question: Complete the MRP plan Lt = 3 , batch size lot for lot ss = 0 C 1 2 3 4 5 6 7 8

Complete the MRP plan

Lt = 3 , batch size lot for lot ss = 0

C 1 2 3 4 5 6 7 8 9 10
Gross Requirements
Scheduled Receipts
Projected On Hand 100
Planned Order Release

D).

LT = 1 Batch size lot for lot , SS = 0

D 1 2 3 4 5 6 7 8 9 10
Gross Requirements 60
Scheduled Receipts
Projected On Hand 30
Planned Order Release

E.)

LT =2 , batch size = L4L , SS = 10

E 1 2 3 4 5 6 7 8 9 10
Gross Requirements 60
Scheduled Receipts
Projected On Hand 50
Planned Order Release

List Actions that should be taken in period 1