Question: Complete the MRP plan Lt = 3 , batch size lot for lot ss = 0 C 1 2 3 4 5 6 7 8
Complete the MRP plan
Lt = 3 , batch size lot for lot ss = 0
| C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Gross Requirements | ||||||||||
| Scheduled Receipts | ||||||||||
| Projected On Hand 100 | ||||||||||
| Planned Order Release |
D).
LT = 1 Batch size lot for lot , SS = 0
| D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Gross Requirements | 60 | |||||||||
| Scheduled Receipts | ||||||||||
| Projected On Hand 30 | ||||||||||
| Planned Order Release |
E.)
LT =2 , batch size = L4L , SS = 10
| E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Gross Requirements | 60 | |||||||||
| Scheduled Receipts | ||||||||||
| Projected On Hand 50 | ||||||||||
| Planned Order Release |
List Actions that should be taken in period 1