Question: Complete the MRP schedule for the part below 6 1. Complete the MRP schedule for the part below. (4 points) Lot size = 1,000+ Safety

Complete the MRP schedule for the part belowComplete the MRP schedule for the part below 6 1.

6 1. Complete the MRP schedule for the part below. (4 points) Lot size = 1,000+ Safety stock = 350 Lead time = 2 weeks Allocated = 150 On hand = 1000 Week 1 2 3 Gross requirements 800 400 Scheduled Receipts 500 Available Net requirements Planned order receipts Planned order releases 4 5 800 1250 900