Question: Complete the Projected on Hand Inventory row. Item - Road Bike A 1 | 2 | 3 | 4 [Gross Requirements] 15 | 40 |

Complete the Projected on Hand Inventory row. Item - Road Bike A 1 | 2 | 3 | 4

[Gross Requirements] 15 | 40 | 40 | 10

[Schedule Receipts] __ | 50 | __ | __

[Projected on Hand Inventory-40] __ | __ | __ | __

[Planned Order Releases] 25 | __ | __ | __

Q = 25; LT = 3; SS = 10