Question: Table 3 Item - Road Bike A 1 2 3 4 Gross Requirements 15 40 40 10 Schedule Receipts 50 Projected on Hand Inventory 40

  1. Table 3

    Item - Road Bike A

    1

    2

    3

    4

    Gross Requirements

    15

    40

    40

    10

    Schedule Receipts

    50

    Projected on Hand Inventory

    40

    Net Requirements

    Planned Order Releases

    Q = 25; LT = 2; SS = 10

    What is the projected on-hand inventory in week 1

    A.

    25

    B.

    30

    C.

    20

    D.

    40

  2. Based on Table 3, what is net requirement in week 3

    A.

    15

    B.

    30

    C.

    25

    D.

    20

  3. Based on Table 3, what is projected on hand inventory in week 3?

    A.

    25

    B.

    15

    C.

    20

    D.

    30

  4. Based on Table 3, what is planned order release in week 1

    A.

    15

    B.

    20

    C.

    25

    D.

    30

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock