Question: Complexity Weighting Scheme: Element Total Number of inputs = Number of outputs 9= Number of inquiries = Number of files = Number of interfaces 15=

Complexity Weighting Scheme: Element Total Number of inputs = Number of outputs 9= Number of inquiries = Number of files = Number of interfaces 15= Low Average High 3 x4 2 3 4 6 x 3 6 x 2 4 6 5 8 12 10 x Using the "Complexity Weighting Scheme" and the function point "Complexity Weighted Table", estimate the total function point count. Assume five function points equal one person a month. If the project must be completed in three years, how many people will be needed for the project? 5 people 3 people 9 people 7 people