Question: Compute the critical path ID Task Duration Predecessor Additional Lag Relationships Lag A Post Signs 1 B Prepare Site 3 A Finish-Start A to B
- Compute the critical path
| ID | Task | Duration | Predecessor | Additional Lag Relationships | Lag |
| A | Post Signs | 1 |
|
|
|
| B | Prepare Site | 3 | A | Finish-Start A to B | 12 |
| C | Lights | 1 | B |
|
|
| D | Dig Trenches | 5 | B |
|
|
| E | Lay Pipe | 5 | D | Start-Start D to E | 3 |
| F | Back Fill | 3 | E | Start-Start E to F | 3 |
| G | Pave | 2 | F |
|
|
| H | Paint Parking Lines | 1 | G | Finish-Start G to H | 1 |
| I | Signage | 1 | F |
|
|
| J | Open Lot | 1 | C,H,I |
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
