Question: Compute the critical path ID Task Duration Predecessor Additional Lag Relationships Lag A Post Signs 1 B Prepare Site 3 A Finish-Start A to B

  1. Compute the critical path

ID

Task

Duration

Predecessor

Additional Lag Relationships

Lag

A

Post Signs

1

B

Prepare Site

3

A

Finish-Start A to B

12

C

Lights

1

B

D

Dig Trenches

5

B

E

Lay Pipe

5

D

Start-Start D to E

3

F

Back Fill

3

E

Start-Start E to F

3

G

Pave

2

F

H

Paint Parking Lines

1

G

Finish-Start G to H

1

I

Signage

1

F

J

Open Lot

1

C,H,I