Question: From the following information, draw the project network. Compute the early, late, and slack times for each activity. Identify the critical path. ID Task Duration

From the following information, draw the project network. Compute the early, late, and slack times for each activity. Identify the critical path.
ID Task Duration Predecessor Additional Lag Relationships Lag
A Interview users 15
B Define new features 5 A Start-start A to B
Finish-finish A to B 10
3
C Order components 2 B
D Build prototype 8 C, E Finish-start C to D 5
E Test 5 C Finish-start C to E
Finish-finish E to D 4
3
F Field test 10 D