Question: Compute the Function Point using the given table, assume that complexity adjustment factor is the average of Weighted factor. Calculate the project cost and estimated
Compute the Function Point using the given table, assume that complexity
adjustment factor is the average of Weighted factor. Calculate the project cost and estimated
effort if average productivity is 7.5 FP/pm and labor rate is Rs. 50000/- per month.
Measurement Parameter Count Weighted factor
Number of external inputs (EI) 32 4
Number of external outputs (EO) 60 5
Number of external inquiries (EQ) 24 4
Number of internal files (ILF) 8 10