Question: Compute the hourly overall system capacity given the production system shown below. The additional rework time and defect rates are provided in the figure below:
Compute the hourly overall system capacity given the production system shown below. The additional rework time and defect rates are provided in the figure below: A A Station A t = 4 min m=1 20 Units/Hr None of the above/below 10 Units/Hr 9 Units/Hr O 12 Units/Hr 40% O 5 Units/Hr Station A t = 2 min 60% 5 min A Station A t = 6 min m=1 A Station A t = 1 min m=1 10% 15 min
Compute the hourly overall system capacity given the production system shown below. The additional rework time and defect rates are provided in the figure below: 20 Units /Hr None of the above/below 10 Units /Hr 9 Units /Hr 12 Units/Hr 5 Units/Hi