Question: Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is

Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent 1 2 3 4 5 Time: Cash flow: - 140 - 140 e 230 205 180 Multiple Choice $143.91 O $205 35 $129.65 O $410.04 O