Question: Compute the total direct cost for each project duration if the indirect costs for each project duration are $400 (19 time units), $350 (18), $300
Compute the total direct cost for each project duration if the indirect costs for each project duration are $400 (19 time units), $350 (18), \$300 (17), and \$250 (16). Plot the total direct, indirect, and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project? What is this cost