Question: Computer Systems Limited is currently deploying a nationwide CRM software system across all its retail outlets. Upon examination, the company realized it can reduce project

Computer Systems Limited is currently deploying a
nationwide CRM software system across all its retail
outlets. Upon examination, the company realized
it can reduce project duration by deploying additional
resources. However, this involves additional
costs. Table 7.5 contains information about cost and
schedule.
Analyzing CostTime Trade-offs
Activity Immediate Predecessor(s) Normal Time (wks) Crash Time (wks) Normal Cost ($) Crash Cost ($)
A 415,0008,000
B 538,00010,000
C A 114,0004,000
D B 636,00012,000
E B, C 764,0007,000
F D 764,0007,000
TABLE 7.7| DATA FOR THE BILLING PROCESS PROJECT
Activity Predecessor (s)
Normal
Time
(months)
Crash
Time
(months)
Cos to Crash
(/month)
A None 54300
B None 108350
C A 53300
D A 4
E B 1
F C, D 1
G D, E 21500
H F 21500
I G 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!