Question: Computer Systems Limited is currently deploying a nationwide CRM software system across all its retail outlets. Upon examination, the company realized it can reduce project
Computer Systems Limited is currently deploying a nationwide CRM software system across all its retail outlets. Upon examination, the company realized it can reduce project duration by deploying additional resources. However, this involves additional costs. Table 7.5 contains information about cost and schedule.
What would be the impact of crashing the project schedule in terms of duration and costs?
Normal Time Activity Predecessor (s) (months) A None 5 None 10 A 5 A 4 B 1 C, D 1 D, E 2 F 2 G 1 B C D E F LL (5) G H I Crash Time (months) 4 8 3 T - 1 1 - Cos to Crash (/month) 300 350 300 500 500
Step by Step Solution
3.28 Rating (151 Votes )
There are 3 Steps involved in it
To determine the total cost and the optimal duration for the project we need to calculate the normal and crash costs for each activity and then find t... View full answer