Question: Computers are assembled in a process with two resources. The processing time of the first resource is 15 minutes. The processing time of the
Computers are assembled in a process with two resources. The processing time of the first resource is 15 minutes. The processing time of the second resource is 13 minutes. The first resource has 5 workers and the second resource has 7 workers. The cycle time of the process is 15.8 minutes. What is the average labor utilization (%)? Note: Round your answer to 1 decimal place. Average labor utilization percent