Question: Computing Problem Assembly Line Performance Auto Link PR , INC. You want to produce 4 0 0 links per day to satisfy the demand of

Computing Problem Assembly Line Performance
Auto Link PR, INC. You want to produce 400 links per day to satisfy the demand of one of your clients. According to the work shift, of 8 hours per day each employee will take a total of 1 hour per shift to rest, eat, etc., resulting in 7 net hours of work per day. The sum of the times of the tasks necessary to produce a linket is 5 minutes per linket. Calculate the minimum number of workstations.