Question: Conceptual Question 1 9 - 1 A project has four activities that take 4 , 3 , 6 , and... A project has four activities

Conceptual Question 19-1 A project has four activities that take 4,3,6, and...
A project has four activities that take 4,3,6, and 7 days, respectively. What is the total completion time for the project?
multiple choice
3 days, because this is the minimum time
7 days, because this is the maximum time
20 days, because this is the sum of the times
It is not possible to determine the total completion time from the given information