Question: Question Content Area Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for

Question Content Area

Problem 12-09 (Algorithmic)

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity Activity Time (weeks) Probability
A 4 0.29
5 0.39
6 0.29
7 0.03
B 8 0.15
10 0.52
12 0.33
C 7 0.09
9 0.22
11 0.42
13 0.20
15 0.07
D 11 0.60
13 0.40

  1. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
    Activity Base case Worst case Best case
    A fill in the blank 1 weeks fill in the blank 2 weeks fill in the blank 3 weeks
    B fill in the blank 4 weeks fill in the blank 5 weeks fill in the blank 6 weeks
    C fill in the blank 7 weeks fill in the blank 8 weeks fill in the blank 9 weeks
    D fill in the blank 10 weeks fill in the blank 11 weeks fill in the blank 12 weeks
    Total fill in the blank 13 weeks fill in the blank 14 weeks fill in the blank 15 weeks
  2. Use the random numbers 0.5753, 0.1426, 0.3989 and 0.255 to simulate the completion time of the project in weeks.
    Activity Random Number Completion Time
    A 0.5753 fill in the blank 16 weeks
    B 0.1426 fill in the blank 17 weeks
    C 0.3989 fill in the blank 18 weeks
    D 0.255 fill in the blank 19 weeks
    Total fill in the blank 20 weeks
  3. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less. Simulation provides a distribution of project completion times. The (mean or percentage)of times weeks and under can be used to estimate the probability that the project will be completed within weeks.

Question Content Area Problem 12-09 (Algorithmic) A project has four activities (A,B, C, and D) that must be performed sequentially. The probability distributionsfor the time required to complete each of the activities are as

Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity A B D Activity Time (weeks) 4 5 6 7 8 10 12 7 9 11 13 15 11 13 Probability 0.29 0.39 0.29 0.03 0.15 0.52 0.33 0.09 0.22 0.42 0.20 0.07 0.60 0.40 a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project. Activity Base case A B C D Total C D Total 0.5753 0.1426 weeks weeks 0.3989 weeks 0.255 weeks Activity Random Number Completion Time A weeks B weeks Worst case weeks b. Use the random numbers 0.5753, 0.1426, 0.3989 and 0.255 to simulate the completion time of the project in weeks. weeks weeks weeks weeks weeks weeks Best case weeks weeks weeks weeks weeks weeks weeks c. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less. Simulation provides a distribution of project completion times. The and under can be used to estimate the probability that the project mean percentage of times weeks in weeks. Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity A B D Activity Time (weeks) 4 5 6 7 8 10 12 7 9 11 13 15 11 13 Probability 0.29 0.39 0.29 0.03 0.15 0.52 0.33 0.09 0.22 0.42 0.20 0.07 0.60 0.40 a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project. Activity Base case A B C D Total C D Total 0.5753 0.1426 weeks weeks 0.3989 weeks 0.255 weeks Activity Random Number Completion Time A weeks B weeks Worst case weeks b. Use the random numbers 0.5753, 0.1426, 0.3989 and 0.255 to simulate the completion time of the project in weeks. weeks weeks weeks weeks weeks weeks Best case weeks weeks weeks weeks weeks weeks weeks c. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less. Simulation provides a distribution of project completion times. The and under can be used to estimate the probability that the project mean percentage of times weeks in weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!