Question: Conflicts between two mutually exclusive projects, where the NPV method chooses one project but the IRR method chooses the other, should generally be resolved in
Conflicts between two mutually exclusive projects, where the NPV method chooses one project but the IRR method chooses the other, should generally be resolved in favor of the project with the higher NPV.
For each statement, please indicate whether you agree or disagree with the statement (ie, true/false) and, in 1-3 sentences or a mathematical theorem, explain why you agree or disagree. If you think the statement is false, you can correct it to make it true. If the statement is true, use evidence or an example