Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s)...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A 4 0 4 0 4 0 B A 10 10 C A 1 4 8 D B 4 10 14 10 0 E B, C 3 10 13 10 13 0 F C 5 8 13 3 G E, F 1 13 14 13 0 8 What is the duration of activity B? The duration of activity B is What is the project duration? The project duration is days. days. What are the critical activities? (Enter your answer as a sequence of capital letters with no dashes or spaces.) The critical activities are Consider the following crash data for a project. Times are given in weeks. NORMAL CRASH NORMAL ACTIVITY TIME TIME COST ($) CRASH COST ($) A 4 4 7,700 7,700 B 5 2 1,200 3,300 C 13 5 3,400 4,200 D 3 1 3,400 3,800 E 10 2 5,700 7,300 F 8 4 2,600 3,000 How many week(s) of crashing are available for activity C in the table above? Activity C has weeks of crashing available. What will be the cost of activity C if it is completed in 7 weeks? The cost will be $. Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A 4 0 4 0 4 0 B A 10 10 C A 1 4 8 D B 4 10 14 10 0 E B, C 3 10 13 10 13 0 F C 5 8 13 3 G E, F 1 13 14 13 0 8 What is the duration of activity B? The duration of activity B is What is the project duration? The project duration is days. days. What are the critical activities? (Enter your answer as a sequence of capital letters with no dashes or spaces.) The critical activities are Consider the following crash data for a project. Times are given in weeks. NORMAL CRASH NORMAL ACTIVITY TIME TIME COST ($) CRASH COST ($) A 4 4 7,700 7,700 B 5 2 1,200 3,300 C 13 5 3,400 4,200 D 3 1 3,400 3,800 E 10 2 5,700 7,300 F 8 4 2,600 3,000 How many week(s) of crashing are available for activity C in the table above? Activity C has weeks of crashing available. What will be the cost of activity C if it is completed in 7 weeks? The cost will be $.
Expert Answer:
Posted Date:
Students also viewed these general management questions
-
Given, R = 192 R = 22 C=2F C=4F (1) V www R www R R R C The time constants (in S) for the circuits I, II, III are respectively (A) 18, 8/9, 4 (C) 4, 8/9, 18 (II) (B) 18, 4, 8/9 (D) 8/9, 18, 4 R3 (III)
-
Below is information from the statement of retained earnings of Mrs. Bells Pastry, Inc. Dividends .....................$ 0 Net income ................... ? Retained earnings, January 31, 2011...
-
Castlevania Company lost most of its inventory in a fire in December just before the year-end physical inventory was taken. The corporation's books disclosed the following. Beginning inventory...
-
Using the information from Review 4-1, answer the following questions. a. Calculate the total cycle time of this manufacturing process. b. Calculate the manufacturing cycle efficiency of this...
-
Allocation of common costs. Jim Dandy Auto Sales uses all types of media to advertise its products (television, radio, newspaper, etc.). At the end of 2011, the company president, Jim Dandridge,...
-
The question prompt states that otters are visual predators who are most successful at hunting the most common color phenotype based on their search image. Given that most clams in the initial...
-
reply to: Cost control measures will be implemented to avoid exceeding the allocated budget while prioritizing critical VMI functionalities. The commitment to Corporate Social Responsibility (CSR) is...
-
Provide an alternate perspective on the advantages of using SWOTT over SWOT analysis. Identify an additional aspect of the environmental analysis not covered by SWOTT that would be important to...
-
The graph of y = f(x) is shown below. What are all of the real solutions of f(x) = o? 2 -10 14 4 9 8 10
-
2. Kofi is interested in the effect of the introduction of the Free Senior High School (Free -SHS) in the Ghana on the unemployment rate (Number of unemployed/ Labour force) and applies a...
-
Find the page in the slides, with the code below and the corresponding memory drawing. How many boxes are drawn and what is the total memory used (the sum of the sizes of those boxes)? struct node *...
-
Discuss the key advantages and disadvantages of the various payment methodologies for hospitals from the point of view of a managed care plan, by type of plan. Perform the same exercise, but from the...
-
Answer the following questions (taken from NIEE Case Study). a). On Freds first day, Wally says Were fast at Phaust. How might engineering decisions be affected by a corporate culture that emphasizes...
-
B.) What is the approximate concentration of free Zn 2+ ion at equilibrium when 1.0010 -2 mol zinc nitrate is added to 1.00 L of a solution that is 1.080 M in OH - . For [Zn(OH) 4 ] 2- , K f = 4.610...
Study smarter with the SolutionInn App