Question: Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A - 3

Conider the project schedule shown in the table below. Times are given in days.

Activity

Predecessor(s)

Duration

ES

EF

LS

LF

Slack

A

-

3

0

3

0

3

0

B

A

5

7

C

A

5

3

8

D

B

8

5

13

7

2

E

B, C

3

8

11

8

11

0

F

C

2

9

11

1

G

E, F

4

11

15

11

0

What is the EF time for activity F?

The EF time for activity F is

nothing

days.

What is the project duration?

The project duration is

nothing

days.

What are the critical

activities?

(Enter your answer as a sequence of capital letters with no dashes or spaces.)

The critical activities are

nothing.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!