Question: Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A - 3
Conider the project schedule shown in the table below. Times are given in days.
| Activity | Predecessor(s) | Duration | ES | EF | LS | LF | Slack |
| A | - | 3 | 0 | 3 | 0 | 3 | 0 |
| B | A | 5 | 7 | ||||
| C | A | 5 | 3 | 8 | |||
| D | B | 8 | 5 | 13 | 7 | 2 | |
| E | B, C | 3 | 8 | 11 | 8 | 11 | 0 |
| F | C | 2 | 9 | 11 | 1 | ||
| G | E, F | 4 | 11 | 15 | 11 | 0 |
What is the EF time for activity F?
The EF time for activity F is
nothing
days.
What is the project duration?
The project duration is
nothing
days.
What are the critical
activities?
(Enter your answer as a sequence of capital letters with no dashes or spaces.)
The critical activities are
nothing.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
