Question: Conrad Weitzel considers himself a conservative project manager, so he never accepts deadlines that provide a safety margin below 85%. The Project Management software used
Conrad Weitzel considers himself a conservative project manager, so he never accepts deadlines that provide a safety margin below 85%. The Project Management software used by your company estimates a new project has an average duration of 40 weeks and a standard deviation of 2.5 weeks. Given Mr. Weitzel`s assumption, what would the most appropriate duration for the project be
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts