Question: Consider a 3-stage sequential batch process. Assume there exists unlimited demand for the product. The resource at stage 3 is a machine that needs a

Consider a 3-stage sequential batch process.Consider a 3-stage sequential batch process.

Consider a 3-stage sequential batch process. Assume there exists unlimited demand for the product. The resource at stage 3 is a machine that needs a setup each time it produces a batch of 40 units. Resource 1 Resource 2 Resource 3 Stage Setup Time (min) Processing Number of Time Workers (minutes/unit) 6 1 1 none NE 3 2 none 3 10 *NA- not applicable 2 NA* 5 What is the utilization of Stage 3? (Hint: Utilization = flow rate x processing time of Resource 3.) 11.43% 75% 30% 80% O 100%