Question: Consider a 3-stage sequential batch process. Assume there exists unlimited demand for the product. The resource at Stage C is a machine that needs a

Consider a 3-stage sequential batch process. Assume there exists unlimited demand for the product. The resource at Stage C is a machine that needs a setup each time it produces a batch of 80 units.

Stage Set up time processing time number of workers

A. None. 6 2

B. None. 6 1

C. 10. 5 NA

Suppose the batch size is 80. Which of the following will increase process capacity?

1. Add one worker to Stage B.

2. Move one worker from Stage A to Stage B.

3. Add another identical machine to Stage C. 4. Do nothing.