Question: Consider a 3-stage sequential batch process. Assume there exists unlimited demand for the product. The resource at Stage C is a machine that needs a
Consider a 3-stage sequential batch process. Assume there exists unlimited demand for the product. The resource at Stage C is a machine that needs a setup each time it produces a batch of 80 units.
Stage Set up time processing time number of workers
A. None. 6 2
B. None. 6 1
C. 10. 5 NA
Suppose the batch size is 80. Which of the following will increase process capacity?
1. Add one worker to Stage B.
2. Move one worker from Stage A to Stage B.
3. Add another identical machine to Stage C. 4. Do nothing.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts