Consider a 3-stage serial process consisting of Stage A, Stage B, and Stage C, whose processing times
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider a 3-stage serial process consisting of Stage A, Stage B, and Stage C, whose processing times are 5 min/unit, 7 min/unit, and 6 min/unit, respectively. What is the minimum cycle time of the process?