Question: Consider a balanced line consisting of five single - machine stations with exponential process times. Suppose the utilization is 7 5 percent and the line

Consider a balanced line consisting of five single-machine stations with exponential process times. Suppose the utilization is 75 percent and the line runs under the CONWIP protocol (i.e., a new job is started each time a job is completed).
What is the WIP level in the line?
What is the cycle time as a percentage of T0?
What happens to WIP, CT, and TH relative to the original system if you make each of the following changes (one at a time)?
Increase the WIP level
Decrease the variability of one station
Decrease the capacity at one station
Increase the capacity of all stations

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!