Question: . Consider a balanced line consisting of five single-machine stations with exponential process times. Suppose the utilization is 75 percent and the line runs under

. Consider a balanced line consisting of five single-machine stations with exponential process times. Suppose the utilization is 75 percent and the line runs under the CONWlP protocol (i.e., a new job is started each time a job is completed).

a. What is the WlP level in the line?

b. What is the cycle time as a percentage of To?

c. What happens to WIP, CT, and TH relative to the original system if you make each of the following changes (one at a time)?

i. Increase the WIP level ii. Decrease the variability of one station iii. Decrease the capacity at one station iv. Increase the capacity of all stations

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!