Question: (!)Consider a factory that runs one shift per day from 7:00 a.m. to 4:00 p.m. The company produces hardware with one large press. The company

(!)Consider a factory that runs one shift per day from 7:00 a.m. to 4:00 p.m.

The company produces hardware with one large press.

The company provides a 30 minute lunch break and two 15 minute coffee breaks

During this one shift, the machine was down 5 times for 11, 15, 6, 20 and 4 minutes.

The machine produced 7,500 parts on this shift.

Ideal process time for this machine is 3 seconds per part.

Quality Control rejected 173 parts from this production run

Calculate the Overall Equipment Effectiveness for this one machine.

options:

0.663

0.914

0.763

0.883

(2)Your dispensing process historically yields a mean of 2540 ml with a standard deviation of 71 ml.

Customer Specification limits are 2400 to 2600ml.

What is the sigma level for this process?

Question 6 options:

3.5 sigma

0.7 sigma

2.3 sigma

4.2 sigma

(3)Your dispensing process yields a mean of 2540 ml with a standard deviation of 71 ml.

Customer Specification limits are 2400 to 2600ml.

What is your Cp lower?

Question 8 options:

0.486

0.282

0.657

0.188

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!