Question: Consider a four - month long project having activities and schedule as per following table. You are Project Manager of this project and want to
Consider a fourmonth long project having activities and schedule as per following
table. You are Project Manager of this project and want to monitor and control it with
the help of Earned Value Management techniques. Analyse the project at the end of
March month and assume Earned Value Actual Cost to
answer following questions:
Find out PV BAC budget at completion SV CV SPI, and CPI.
How can you find the chances of project success? Calculate the relevant Index.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
