Question: Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this
Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process.
Step 1: 16 minutes per unit
Step 2: 15 minutes per unit
Step 3: 22 minutes per unit
Step 4: 12 minutes per unit
Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 98 units?
Note: Do not round intermediate calculations. Round your answer to nearest hour.