Question: Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this
Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process.
Step 1: 25 minutes per unit
Step 2: 15 minutes per unit
Step 3: 30 minutes per unit
Step 4: 20 minutes per unit
Round your answer to 3 digits after the decimal point if it is not an integer. Do NOT use comma in your numeric answers.
The resource capacity of step 2 is ______units per hour.
The resource capacity of step 4 is _______ units per hour.
The process capacity is _______units per hour.
Assume unlimited demand, the cycle time is ________hours.
Assume that the process starts out empty. It will take_________ hours for the first flow unit to go through an empty system, and it will take a total of _______ hours to complete a batch of 105 units.