Question: Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this
Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process.
Step 1: 25 minutes per unit
Step 2: 15 minutes per unit
Step 3: 30 minutes per unit
Step 4: 20 minutes per unit
Round your answer to 3 digits after the decimal point if it is not an integer. Do NOT use comma in your numeric answers.
1. The resource capacity of step 2 is [ ] units per hour.
2. The resource capacity of step 4 is [ ] units per hour.
3. The process capacity is [ ] units per hour.
4. Assume unlimited demand, the cycle time is [ ] hours.
5. Assume that the process starts out empty. It will take [ ] hours for the first flow unit to go through an empty system, and it will take a total of [ ] hours to complete a batch of 105 units.