Question: Consider a line process with 3 processing stages. The production requires each unit to go through Stage A through Stage C in sequence. The characteristics

Consider a line process with 3 processing stages. The production requires each unit to go through Stage A through Stage C in sequence. The characteristics of the Stages are given below: Stage A B C Unit processing time(minutes) 1 2 3 Number of machines 1 1 1 Machine availability 90% 100% 100% Process yield at stage 80% 50% 50% Defective units produced at each stage will be scrapped before passing onto the next stage. Determine the system capacity (in good units per hour). Which stage is the bottleneck?