Question: Consider a line process with 3 processing stages. The production requires each unit to go through Stage A through Stage C in sequence. The characteristics
Consider a line process with 3 processing stages. The production requires each unit to go through Stage A through Stage C in sequence. The characteristics of the Stages are given below: Stage A B C Unit processing time(minutes) 1 2 3 Number of machines 1 1 1 Machine availability 90% 100% 100% Process yield at stage 80% 50% 50% Defective units produced at each stage will be scrapped before passing onto the next stage. Determine the system capacity (in good units per hour). Which stage is the bottleneck?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts