Question: Consider a line process with 3 processing stages. The production requires each unit to go through Stage A through Stage C in sequence. The characteristics
Consider a line process with 3 processing stages. The production requires each unit to go through Stage A through Stage C in sequence. The characteristics of the Stages are given below: Stage A B C Unit processing time(minutes) 1 2 3 Number of machines 1 1 2 Machine availability 90% 100% 100% Process yield at stage 100% 100% 100% Determine the system capacity. Which stage is the bottleneck? What is the utilization of Stage 3.