Question: Consider a network diagram. The top middle box in the Activity on Node box is typically: 1 . The Float 2 . The Earliest Finish

Consider a network diagram. The top middle box in the Activity on Node box is typically:
1.
The Float
2.
The Earliest Finish Time
3.
The Duration
4.
The Earliest Start Time
5.
The Latest Start Time