Question: Consider a problem with five jobs (A, B, C, D, and E) and two machines M1 and M2. All five jobs consist of two operations

Consider a problem with five jobs (A, B, C, D, and E) and two machines M1 and M2. All five jobs consist of two operations each. The first operation of each job is processed on machine M1; and the second operation is processed on machine M2. The following table gives the processing times in hours for each operation of each job.

Consider a problem with five jobs (A, B, C, D,

A) Determine the optimal sequence.

B) Determine the optimal makespan

PLEASE DO NOT FOLLOW MANUAL SOLUTION ONLINE AS MACHINE 1 PROCESSING TIME FOR JOB D HERE IS 4 AND NOT 7 LIKE MANUAL SOLUTION.

Job Machine 1 Machine 2 A 8 3 3 B 5 7 6 9 D 4 1 E 7 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!