Question: Consider a problem with five jobs (A, B, C, D, and E) and two machines M1 and M2. All five jobs consist of two operations
Consider a problem with five jobs (A, B, C, D, and E) and two machines M1 and M2. All five jobs consist of two operations each. The first operation of each job is processed on machine M1; and the second operation is processed on machine M2. The following table gives the processing times in hours for each operation of each job.

A) Determine the optimal sequence.
B) Determine the optimal makespan
PLEASE DO NOT FOLLOW MANUAL SOLUTION ONLINE AS MACHINE 1 PROCESSING TIME FOR JOB D HERE IS 4 AND NOT 7 LIKE MANUAL SOLUTION.
Job Machine 1 Machine 2 A 8 3 3 B 5 7 6 9 D 4 1 E 7 6Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts