Question: Consider a process consisting of... Consider a process consisting of three resources. Assume there exists unlimited demand for the product, and that all activities are
Consider a process consisting of...
Consider a process consisting of three resources. Assume there exists unlimited demand for the product, and that all activities are always performed in the following sequence.
Resource 1 has a processing time of 5 minutes per unit.
Resource 2 has a processing time of 2 minutes per unit.
Resource 3 has a processing time of 4 minutes per unit.
All three resources are staffed by one worker and each worker gets paid $13 per hour.
| Do not round your intermediate calculations. Round your answer to 2 decimal places. |
| a. What is the cost of direct labor? per unit |
| Do not round your intermediate calculations. Round your answer to nearest whole number. |
| b. What is the labor content? minutes per unit |
| Do not round your intermediate calculations. Round your answer to 2 decimal places. |
| d. Assume the demand rate is 24 units per hour. What is the takt time? minutes per unit |
| Do not round your intermediate calculations. Round your answer to 2 decimal places. |
| e. Assume the demand rate is 24 units per hour. What is the target manpower? employees |
| Do not round your intermediate calculations. Round your answer to 1 decimal place. |
| f. If one additional worker could be hired, to which resource should the |
| additional resources be assigned? Calculate the process capacity. units per hour |
| Do not round your intermediate calculations. Round your answer to 1 decimal place. |
| g. If they could take 1 minute of task time from one resource and give it to another |
| resource (so the labor content remains the same), What would be the new capacity of the process (units per hour)? Assume that there is still only 1 worker per station. units per hour |
| Do not round your intermediate calculations. Round your answer to 1 decimal place. |
| h. What would be the capacity of the process if they integrated the work so that all workers do all three tasks (units per hour)? Assume that there is still only 1 worker per station. units per hour |