Question: Consider a process consisting of Three activities, A, B & C taking on average 10 min. each One inspection activity (1) taking 4 minutes to

Consider a process consisting of Three

Consider a process consisting of Three activities, A, B & C taking on average 10 min. each One inspection activity (1) taking 4 minutes to complete. X% of the jobs are rejected at inspection and sent for rework 0.75 A (10) B (10) I (4) (10) 47 0.25 What is the average cycle time? a) If no jobs are rejected and sent for rework. b) If 25% of the jobs need rework but never more than once. c) If 25% of the jobs need rework but reworked jobs are no different in quality than ordinary jobs. 12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!