Question: Consider a process consisting of three resources. Each resource is staffed by two workers. Assume the demand rate is 10 units per hour. Resource 1
Consider a process consisting of three resources. Each resource is staffed by two workers.
Assume the demand rate is 10 units per hour.
- Resource 1 has a processing time of 10 minutes per unit.
- Resource 2 has a processing time of 8 minutes per unit.
- Resource 3 has a processing time of 6 minutes per unit.
- What is the idea cycle time to meet the demand?
- What is the target manpower?
- Assume the workers are paid $20 per hour. What is the cost of direct labor per unit?