Question: Consider a process consisting of three resources: Resource Processing Time Number of Workers [Min./Unit] 1 30 3 2 15 1 3 16 4 (a) What

Consider a process consisting of three resources:

Resource Processing Time Number of Workers

[Min./Unit]

1 30 3

2 15 1

3 16 4

(a) What is the bottleneck?

Bottleneck is: ________

(b) What is the process capacity?

Process Capacity: ________ units/hr

(c) What is the flow rate if demand is three units per hour?

Flow Rate:_______ units/hr

(d) What is the utilization of each resource if demand is three units per hour?

(Round the answers to 2 decimal places.)

Resource 1 - Utilization: _______ %

Resource 2 - Utilization: _______ %

Resource 3 - Utilization: _______ %

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!