Question: (Process Analysis with One Flow Unit) Consider a process consisting of three resources: resource processing time (per minute) no. of workers 1 10 2 2
(Process Analysis with One Flow Unit) Consider a process consisting of three resources:
| resource | processing time (per minute) | no. of workers |
| 1 | 10 | 2 |
| 2 | 6 | 1 |
| 3 | 16 | 3 |
What is the bottleneck? What is the process capacity? What is the flow rate if demand is eight units per hour? [3.2] What is the utilization of each resource if demand is eight units per hour?