Question: Consider a process that has three stages: Stage 1 takes each worker 1 0 minutes to complete. Stage 2 takes each worker 5 minutes to

Consider a process that has three stages:
Stage 1 takes each worker 10 minutes to complete.
Stage 2 takes each worker 5 minutes to complete.
Stake 3 takes each worker 16 minutes to complete.
You have 6 workers.
How would you assign workers to maximize your capacity? Assume you cannot merge any two stages, and workers have to be dedicated on fy to that stage. In other words, workers cannot "float" between stages if they have free time.
Number of workers assigned to:
Stage 1:
Stage 2:
Stage 3: