Question: Consider a process with 4 processing stations as shown below A 12min ---> B 10min -----> C 16min -----> D 8min Currently each of the

Consider a process with 4 processing stations as shown below

A 12min ---> B 10min -----> C 16min -----> D 8min

Currently each of the machines (one worker per machine) work completely during the 8 hour shift. The piling up of inventory between various stations had prompted the company to hire you as a consultant to solve the problem. After a simple process analysis, using principles of Synchronous manufacturing, you have suggested the following Reduce capacity utilisation of A, B and D to 75%, 62.5% and 50% levels. The workers adopted the suggestion in the following way A) Worker of Machine A started the machine late so that he can work continuously B) Worker of Machine B decided to do clean up the machine for 20-25 minutes after every hour of working C) Worker D had offered the management to take up an extra work during the last four hours of the shift What will be the effect of these decisions on the factory performance? How many of these decisions are feasible to implement. How will you solve the problem

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!