Question: Consider a process with a unit cost of $ 2 5 0 for the first unit and a learning rate of 0 . 8 .

Consider a process with a unit cost of $250 for the first unit and a learning rate of 0.8. What will be the unit cost for the 29th unit?
Multiple Choice
$200.00
$138.74
$84.56
$62.44
 Consider a process with a unit cost of $250 for the