Question: Consider a process with a unit cost of $250 for the first unit and a learning rate of 0.81. What will be the unit cost

Consider a process with a unit cost of $250 for the first unit and a learning rate of 0.81. What will be the unit cost for the 29th unit? $89.28 $84.65 $89.82 $84.56