Question: Consider a project consisting 5 activities: A, B, C, D, E. The dependency matrix the defines their relations are shown below: Predecessor activity (upstream) A
Consider a project consisting 5 activities: A, B, C, D, E. The dependency matrix the defines their relations are shown below:
| Predecessor activity (upstream) | ||||||
| A | B | C | D | E | ||
| Successor activity (downstream) | A | |||||
| B | X | |||||
| C | X | |||||
| D | X | |||||
| E | X | X | ||||
Please choose the AON diagram that matches the dependency matrix.
( I CHOSE 2 AND GOT IT WRONG SO I AM CONFUSED)
1.
2.
3.
4.