Question: Consider a project for which AoN network and associated crash data are given as follows. Budget for crashing the project is limited to 5
Consider a project for which AoN network and associated crash data are given as follows. Budget for crashing the project is limited to 5 thousand dollars. Define your decision variables and construct an LP model in open mathematical form to find minimum project crash completion time with available budget. (24 P) Activity A Normal Time Cost A Time (Days) (thousand $) (Days) 8 4 5 6 8 7 ABCDE 1925 65899 15 B 10 | 2 12 E Crash T Crash Cost Per Day Cost Allowable (thousand $) Crash Days (thousand $) 12 4 1.5 9 2 14 3 18 4 16 3 2 2 NN 2.25 2
Step by Step Solution
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Decision variables Lets define the decision variab... View full answer