Question: Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A C, E 4 2 $2000

Consider a project having the following six activities:

Immediate Max Crash cost

Activity Predecessors Time (weeks) Crash* per week

A C, E 4 2 $2000

B A 6 2 $1000

C none 6 6 N/A

D C 3 2 $1000

E none 5 2 $500

F A, D 5 2 $1250

*Shortest possible time for the task

List the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task.

List all potential paths and durations.

List all the tasks on the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!