Question: Consider a project having the following ten activities: Optimistic Most likely Pessimistic Immediate Time (o) Time (m) Time (p) Activity Predecessors (weeks) (weeks) (weeks) A

Consider a project having the following ten activities: Optimistic Most likely Pessimistic Immediate Time (o) Time (m) Time (p) Activity Predecessors (weeks) (weeks) (weeks) A none 1 5 9 B A 6 6 6 C A 3 5 9 D A 2 4 6 E B, C 4 4 4 F D 4 7 8 G E 2 2 8 H E, F 7 8 9 I F 4 6 9 J G, H, I 3 5 7 (a) What is the expected time for each activity